05
08 '15
| ST. JOHN OF GOD HOSPITAL – WEXFORD PERTH, AUSTRALIA |
||
| Project Period | : | February 2013 – September 2013 |
| Scope of Work | : | Glazed Aluminium Unitized Curtain Wall System Aluminium Composite Panel Cladding and louver |
| Project Area | : | 10,890 sq.m. |
| Project Duration | : | 6 Months |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | 30 September 2013 |
| In-house Project | : | Kaskal Co., Ltd. |
05
08 '15
| ST. JOHN OF GOD – NEW SOUTH WING PERTH, AUSTRALIA |
||
| Project Period | : | October 2013 – December 2013 |
| Scope of Work | : | Glazed Aluminium Unitized Curtain Wall System Aluminium Composite Panel Cladding and Louver |
| Project Area | : | 4,639 sq.m. |
| Project Duration | : | 3 Months |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | 16 December 2013 |
| In Collaboration With | : | Kaskal Co., Ltd. |
30
07 '15
| JUSTICE PRECINCT ChristChurch, NZ |
|
SERVICES APPLIED
|
30
07 '15
| BITEC 2 Bangkok, Thailand |
||
| Year Completed | : | 2016 |
| DESIGN | : | KAMA JV Co., Ltd. (Kaskal subsidiary) |
| ENGINEERING | : | Structural analysis and calculation of unitized curtain wall and unitized strip window. |
| FABRICATION | : | Unitized curtain wall, unitized strip window, doors and windows. |
| PERFORMANCE TESTING | : | Unitized curtain wall system using AAMA 501 – 2005, Methods of Test for Curtain Walls. |
30
07 '15
| CANAPAYA RESIDENCES CONDOMINIUM Bangkok, Thailand |
|
SERVICES APPLIED
|
30
07 '15
| ENERGY COMPLEX BUILDING Bangkok, Thailand |
||
| Project Period | : | 2009 – 2007 |
| Scope of Work | : | Glazed Aluminium Unitized Curtain Wall System Aluminium Composite Panel Cladding |
| Project Area | : | 65,000 sq.m. |
| Project Duration | : | 24 Months |
| Project Stage | : | 100% Complete |
| Project Location | : | Bangkok, Thailand |
| In Collaboration With | : | KAMA JV Co., Ltd. |
28
07 '15
| GOVERNMENT CENTER CHAENGWATTANA Bangkok, Thailand |
||
| Project Period | : | 2003 – 2004 |
| Scope of Work | : | Glass Semi-Unitized Window System |
| Project Area | : | |
| Project Duration | : | |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | |
| In Collaboration With | : | Kim Yoo Seng Co., Ltd. |
27
07 '15
| THE 9TH TOWER Bangkok, Thailand |
||
| Project Period | : | 2012 ‐ 2013 |
| Scope of Work | : | Glazed Aluminium Unitized Curtain Wall System Frameless Glass Façade System Aluminium Composite Panel Cladding |
| Project Area | : | 43,4700 sq.m. |
| Project Duration | : | 12 Months |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | 30 September 2013 |
| In Collaboration With | : | KAMA JV Co., Ltd. |
27
07 '15
| SKYWALK Bangkok, Thailand |
||
| Project Period | : | 2003 – 2004 |
| Scope of Work | : | Glazed Aluminium Door and Window System |
| Project Area | : | |
| Project Duration | : | |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | |
| In Collaboration With | : | KAMA JV Co., Ltd. |
27
07 '15
| ORIENTAL RESIDENCES Wireless Road |
||
| Project Period | : | 2010 – 2012 |
| Scope of Work | : | Glazed Aluminium Unitized Curtain Wall System
Doors Windows Aluminium Composite Panel Cladding |
| Project Area | : | 23,000 sq.m. |
| Project Duration | : | 18 Months |
| Project Stage | : | 100% Complete |
| Project Completion Date | : | 31 March 2012 |
| In Collaboration With | : | KYS Co., Ltd. |